| Project ID: |
0092-06-01 |
| Title: |
Perpetual Pavement Instrumentation for the Marquette Interchange Project |
| PI: |
James A. Crovetti
Center for Highway and Traffic Engineering
Marquette University |
| Project: |
Objectives of Phase 1 of this study are to develo and implement a comprehensive pavement instrumentation plan for the HMA perpetual pavement being constructed along the North Leg of the MI project and demeonstrate the capabilities of the instrumentation to provide real-time, off-site recordings of pavement response under construction trafficking. Phase 2 will have us developing and implementing data collection and analysis plans that will ensure the effective storage, retreival, and processing of real-time response data and provide data access to interested pavement researchers and designers. |
| Task List: |
- Literature review
- Develop Field Instrumentation Plan
- Field Installations
- System demonstration
- Phase 1 final report
- Data collection and analysis techniques
- Phase 2 final report
|
| Start Date: |
October 20, 2005 (phase I) |
| End Date: |
January 20, 2007 |
| Extension: |
September 1, 2007, June 30, 2008 (phase II) |
| Project Award: |
$199,937 |
| TOC: |
Flexible Pavements |