Rigid Pavements
Expanded Study on the Effects of Aggregate Coating and Films on Concrete Performance |
| Quarterly Reports |
Additional Documents/Data |
Final Report |
2005-Q2
2005-Q3
2005-Q4
2006-Q1
2006-Q2
2006-Q3
2006-Q4
2007-Q1
2007-Q2
2007-Q3
|
Citations for related TRB papers
Research Brief |
|
| Project ID: |
0092-04-12 |
| Title: |
Expanded Study on the Effects of Aggregate Coating and Films on Concrete Performance |
| PI: |
Steven M. Cramer
Department of Civil and Environmental Engineering
University of Wisconsin-Madison |
| Project: |
An earlier WisDOT study (0092-00 -07) of limited sample size identified certain Wisconsin aggregate coatings that could negatively impact pavement durability. This expanded study will assemble a larger sample size to improve understanding of the impact of coatings and how to minimize that impact. The objectives are to develop a statewide database on aggregate cleanliness and source; identify and verify conditions and locations with unsuitable aggregate cleanliness levels; further test such aggregates to identify coatings, test concrete made from such aggregate, and research methods for detection of deleterious coatings. |
| Task List: |
- Establish a list of properties/criteria needed for a database on course aggregate cleanness in the state
- Update our relevant literature data on aggregate cleanness
- Monitor the WisDOT database of aggregate cleanness based on criteria established in Task 1
- As aggregates are identified that do not meet the proposed criteria, we will conduct follow-on tests to confirm the screening outcome
- Once it is confirmed that the aggregates do not meet the proposed criteria, we will obtain additional aggregates to allow for concrete tests to establish the effect of aggregate coating
- Characterize the aggregate coating with additional testing
- Perform laboratory concrete batching and testing of plastic and hardened concrete
- Report the results of the expanded study
|
| Start Date: |
October 1, 2003 |
| End Date: |
September 30, 2006 |
| Extension: |
August 31, 2007, October 31, 2007 |
| Project Award: |
$149,995 |
| TOC: |
Rigid Pavements |
|