Project 0092-08-37: Implementation of Project Three Different Methods for Determining Pile Bearing Capacities (Completed)
| Quarterly Reports | Additional Documents/Data | Final Report |
|---|---|---|
| Project completed resulted in modifications to section 11.3 of the WisDOT LRFD bridge manual. | ||
| Project ID: | 0092-08-37 | |
| Title: | Implementation of Project Three Different Methods for Determining Pile Bearing Capacities | |
| PI: | James H. Long, Ph.D., P.E. |
|
| Project: | The objective for this effort includes using results from project 0092-07-04 for developing design values, guidance, and tools for the Bridge Manual. Furthermore, it will be essential to work closely with the WisDOT engineers to apply the results of the research LRFD deep foundation design issues in a form that is understandable and usuable for their design needs. | |
| Start Date: | June 23, 2008 | |
| End Date: | June 23, 2009 | |
| Extension: | August 31, 2009, November 11, 2009 | |
| Project Award: | $10,000 | |
| TOC: | Geotechnics | |