Project 0092-08-10: Performance Assessment of Wisconsin's Whitetopping and Ultra-Thin Whitetopping Projects (In Progress)
| Quarterly Reports | Additional Documents/Data | Final Report |
|---|---|---|
|
2007-Q4 |
||
| Project ID: | 0092-08-10 | |
| Title: | Performance Assessment of Wisconsin's Whitetopping and Ultra-Thin Whitetopping Projects | |
| PI: | Haifang Wen Civil and Environmental Engineering Department University of Wisconsin - Madison |
|
| Project: | The primary objectives of this study are to catalog the WT and UTW projects, document pertinent design and construction elements, statistically assess performance of these projects, and estimate a service life for WT and UTW for design and life cycle cost analysis in Wisconsin. | |
| End Date: | October 4, 2007 | |
| End Date: | October 4, 2008 | |
| Extension: | March 30, 2009, December 31, 2009, February 4, 2010, March 31, 2010 | |
| Project Award: | $74,867 | |
| TOC: | Rigid Pavements | |